Restricted dates (Potentially) How to handle them

Mark FairbairnMember for 13 years 10 months
Created
4
2
0

Hi,

 

I am working on a project where there are many locations over a 70km stretch.  Some of these areas potentially have Endangered Animals in them and we cannot work During their mating season (Apr 15 to July 31) if the wildlife experts find any signs of the Endangered Animals in the area during that time.  All work will stop and we will not be able to continue until after July. 

I need to identify those locations so we can do our best to avoid scheduling no work during that time in those locations.  I tried using a calendar for wildlife issues but that did not work as I do not want the schedule dates to be changed I just want to be notified if we have work scheduled at that location at that time.

 

Can you please advise me, ....  should I use "issues"?  If so how?

 

Thank you

Mark

4 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Mark,1. Suggest to use a

    Mark,

    1. Suggest to use a Curtain.

    2. Use Filter Highlight.

    3. Notes.

  2. 0
    Mike Testro ·

    Hi Mark Set up non working

    Hi Mark

    Set up non working days on different calendars and apply them to the required activities.

    Best regards

    Mike Testro

  3. 0
    Gary Whitehead ·

    Mark:   1) Add a code to your

    Mark:

     

    1) Add a code to your activties "Potential Wildlife Issues?" (Y/N)

    2) Create a filter where code = Y

    3) Create a filter "Mating season" where Start is within April 15 to July 31 OR Finish is within April 15 to July 31

    4) Apply both filters

     

    Cheers,

    G

  4. 0
    Mark Fairbairn ·

    Thanks Gary,   I used your

    Thanks Gary,

     

    I used your suggestion and it meets my needs perfectly as I have 5 different variations on "wildlife issues"

     

    I appreciate your help.