Computing Actual cost for activities under progress
In the Open Standard
Sendhil KumarMember for 16 years 2 months
- Created
- 0
- 1
0
Hi all,
I am updating a schedule with some resources assigned. When I update activiites which have started but not completed, I dont get the actual cost after scheduling(F9). I have to go to Tools --> Recalculate Assignment Cost to see my actual cost update for the activity.
Is there any setting I have to do to calculater this cost automatically after scheduling.
Note: Actual cost is computed for completed activities but not for the ones in progress.
Thanks ,
Sendhil