duration % comp doesnt update

Ferhat AciciMember for 13 years 10 months
Created
5
3
0

(first sorry for my  english) i m entering a new value in the duration % comp field then i schedule but p6 doesnt update my new value.p6 hold my old value how can i solve this problem thnx 

5 replies

Oldest first
  1. 0
    Johannes Vandenberg ·

    HiFerhatThere are several

    Hi

    Ferhat

    There are several reasons why the updating of the duration % completion are not showing.

    • The activities to be updated must have % completion type Duration. You can check this by going to the General tab and make sure that duration %  is ticked. Others are units and physical & completion.
    • Make sure that you have assigned the appropriate baseline. When you have made new activities and you have not baselined these activities correctly than the values shall not be updated.

    Regards Johannes

  2. 0
    Ferhat Acici ·

    Hi Johannesmy activity %

    Hi Johannes

    my activity % completion type is duration.And i assigned baseline.i didnt add new activity or delete.but duration % comp doesnt change.i m checked the other projects on p6.on my project  "Link Budget and At completion for not started activities"

    is not active and i cant mark it maybe problem is here?

  3. 0
    Johannes Vandenberg ·

    Hi FerhatIt seems that i

    Hi Ferhat

    It seems that i cannot help you any further . Are you sure that you are displaying the correct column for "duration % completion"? You can check this by verifying whether the % completion in the status tab is the same as the display in the column you are using.

    Maybe  Raymund may have a solution

    Regards

    Johannes

  4. 0
    Raymund de Laza ·

    Ferhat,Had you set the

    Ferhat,

    Had you set the activity as started by checking the check box beside started?

    And are you a poweruser of the program?

  5. 0
    Syed Hussain ·

    Ferhat,Check activity type.

    Ferhat,

    Check activity type. It looks like Activity Type is "WBS Summary". P6 will never let you update the % of WBS Summary activity and it will bring % back when you reschedule.

     

    Syed