Skip to content

LOE activity updating resource units

Kp RaoMember for 15 years 2 months
Created
0
3
0

Hi,

I am using P6 v7.I have a Level of Effort activity with pred and successors.When I update the pred the LOE not taking the actual values.The resource labor units not updating.I am using Duration % complete.

Regards,

kp

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?