Skip to content

A quick question on Duration versus units/time

Scottie BellMember for 15 years 5 months
Created
1
1
0

Hi there. My question is, is there a way to keep my units/time from changing in my resources when i change my original duration. It is frustrating me because i cant figure it out, and am manually having to go back and re adjust my units/time. I thought the answer would be in the duration settings, but i dont know. Is there a way to do it?

Thank you!

Scottie Bell

1 reply

Oldest first
  1. 0
    Scottie Bell ·

    I figured it out-I changed

    I figured it out-

    I changed the duration type from fixed duration & units to fixed duration and units/time. Works great if anyone has the same issue. If your duration type is not set to the correct setting from the start, you will need to go to each individual activity your changing the original duration for, and change duration type in the general tab.

    Have a great day!

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?