Export both Baseline+Current in one XER file?

Jenny IngcoMember for 14 years 9 months
Created
6
2
0

Dear All P6 Experts,

I have my current schedule and I already assigned Basline to it. I try to export my current schedule as XER file and send it by e-mail but the person who import it to his computer he can't see my assigned baseline? Is there method I can send them in correct way at the same time in one XER file?

 

Thank you all,

 

Hanson 

6 replies

Oldest first
  1. 0
    Tony Cabezon ·

    In the maintain baselines

    In the maintain baselines click restore to unlink the baseline, open both and export XER, the other person just needs to assign the baseline to the main project. then later on for updates you´d only need to send the main project and import it as updating.

  2. 0
    Essam AbdulFattah ·

    use refliction in P6 it will

    use refliction in P6 it will include current schedule along with more than one baseline.

     

     

    Essam

  3. 0
    Syed Hussain ·

    How to use refliction? syed

    How to use refliction?

     

    syed

  4. 0
    Dreams2010 Dendy ·

    thanks Tony for your

    thanks Tony for your illustration

  5. 0
    Zoltan Palffy ·

    its alwasy a good practice to

    its alwasy a good practice to copy the original baseline schedule for this exact purpose becasue once you assign it to another schedule it gets hidden.

    as Tony said restore the baseline open both projects together then export 