importing of file to primavera? any help please!

Rajesh DapurkarMember for 15 years 1 month
Created
3
2
0

is there a way to import a XER file from Primavera ver 8.2 toversion 6.2? OR is there a way to import mpp file primavera

 

Regards/Rajesh

3 replies

Oldest first
  1. 0
    Jenny Ingco ·

    Yes, when you export it from

    Yes, when you export it from v 8.2 you will have options in Export format page. so, you may choose 6.2 or any other version you like.

    Thank you,

     

    HANSON

  2. 0
    Mohammad Waseem Anwar ·

    hi planners,1- to open 8.2

    hi planners,

    1- to open 8.2 XER in 6.2 just right click on xer file and open in notepad........on first line written ver 8.2 change in to 6.0 or 6.2 and save .........then open in primavera 6.2 ..................

     

    2-Second.........for MPP files........primavera have standard import opetion available in import for MPP files..........

  3. 0
    V Kutty ·

    Primavera V6 will Import MSP

    Primavera V6 will Import MSP only MSP exptensions .XML or .MPX .

    File - Import -  

     