Cab somebody help me to import P3 PRX file to P6.0

Joseph AdorMember for 16 years 1 month
Created
29
8
0
This is a new job for me on the project and the plannet turnover the programing activities to me but the problem is he is using P3 which is on PRX file. Is it possible i can import it to P6.0? I’ve tried it but P6 can’t find the file.

Can you help me guys whose available there.

Thanks and Best Regards,

Joseph

Happy Planning!!

29 replies

Oldest first
  1. 0
    Jeoffrey Reyes ·
    Hi Joseph,

    In the File Menu....Select File=>Import=>Primavera Project Planner –(P3)…then click next...from the P3.3.x Project Directory browse for your file...Check the box when you see it....then follow succeeding instructions.

    Cheers,
    JEFF
  2. 0
    Joseph Ador ·
    Hi Jeff,

    I try it but i was stopped on browsing under project directory. And I cant even see a check box for my file to select. And P6 said that i didn’t choose any project to import to proceed.
  3. 0
    Jeoffrey Reyes ·
    Hi Joseph,

    Did you click on the button with 3 dots? after clicking that it will show you ...Browse for Folder dialog Box.
  4. 0
    Jeoffrey Reyes ·

    Joseph, Did you Extract your PRX File? If not extract it and put it in another folder and browse from it.
    Cheers,
  5. 0
    Joseph Ador ·
    Hi Jeff,

    Its on a usual folder not inside a zip file. When i come up with the project directory browsing then it stops on the folder without getting inside the folder for PRX file.

    Cheers,
    Joseph
  6. 0
    Jeoffrey Reyes ·
    Joseph, as i said on my last post if you extract your PRX file first?...because PRX file cannot be read.
  7. 0
    Joseph Ador ·
    Hi Jeff,

    No, I didn’t extract it. I just copied the folder from the stick. It was a bit strange that P6 doesn’t recognize the file under the folder.

    Thanks,
  8. 0
    Jeoffrey Reyes ·
    Hi Joseph,

    OK, extract it and you will find your file there.
    Cheers,
    JEFF
  9. 0
    Joseph Ador ·
    Hi Jeff,

    Sorry I can’t find how to extract it since it’s already in a folder need not to be extracted just like what we have in zip files.

    Can you make it clear where im gonna extract it, is it the prima to extract it or im gonna extract it to the folder which i think not possible since it’s already on a folder. Correct me if i’m wrong.

    Cheers,

    Joseph
  10. 0
    Jeoffrey Reyes ·
    Hi Joseph,

    Double Click the file and a dialog box will open for extraction...or Do you have P3 installed? If you have, you can do it there. Tools=>Project utilities=>Restore. let me know. or send me the file i will extract it and i will send it to you all the files.

    Cheers,
  11. 0
    Joseph Ador ·
    Hi Jeff,

    I think it’s better to send you the file. Because i double click it’s trying to open P6 not the extraction box. Can you give your email plss..

    A lot of thanks.

    Cheers,

    Joseph

  12. 0
    Joseph Ador ·
    Hi Jeff,

    I think it’s better to send you the file. Because i double click it’s trying to open P6 not the extraction box. Can you give your email plss..

    A lot of thanks.

    Cheers,

    Joseph

  13. 0
    Jeoffrey Reyes ·
    dyepreyes@yahoo.com
  14. 0
    Jeoffrey Reyes ·
    Hi Joseph,

    Extracted and sent already.

    Cheers,
    JEFF
  15. 0
    Joseph Ador ·
    Thanks Jeff,

    Sorry for my late reply. When i try it again using your extracted file, i came up with an error after check box and prompt me to exit or do more actions. The error display as "An application has been intercepted. Please note the event code for reference AVAA4-2216-F." Can you help me how to make it done from your genius mind?

    Cheers,
    Joseph
  16. 0
    Jeoffrey Reyes ·
    Hi Joseph,

    I opened and checked your file already and I saw what’s inside of it. It is an infra project right? Anyway, I will try to convert it to P6 XER file so it will be easy for you to open.

    Cheers,
    JEFF
  17. 0
    Joseph Ador ·
    Hi Jeff,

    Yes it’s an infra project. I will take over the planning & scheduling works which was done in P3. Can I give you the first week update as well to make it easy for me to use anyone of them. The first one i give you is the project baseline level 3, it’s not detailed. Because I’m having trouble in transferring datas from P3 and then check it again if some of the dates moves.

    Thanks so much Jeff. I will send you 2 P3 file to convert it as an XER. I appreciate your response.

    Best Regards,
    Joseph
  18. 0
    Jeoffrey Reyes ·
    Hi Joseph,

    Ok, i’ll received it. i’ll convert it and send it to you one time.
  19. 0
    Joseph Ador ·
    Hi Jeff,

    I appreciate it. It would be a great help to finish my progress this period.

    Happy Planning!!!

    Cheers,
    Joseph
  20. 0
    Jeoffrey Reyes ·
    Hi Joseph,

    Sent already. Please check your mail.
    Cheers,
  21. 0
    Joseph Ador ·
    Hi Jeff,

    I think your using P6 ver. 7. Mine is P 6 ver 0 only, this software provided by the client. My software can’t manage to import it. Is there any possibility to downgrade it?

    Thanks so much sir for the help. Because this is my first time to import program from P3.

    Cheers,
    Joseph

  22. 0
    Joseph Ador ·
    Hi Jeff,

    One more question, if i will import now the file, do i have to choose the default configuration or i have to modify it make sure that all activities, resources, calendar, act. Id’s, and etc are still the same? Because in modify they offer what do you want to update and what to keep on the existing file.

    Cheers,

    Joseph
  23. 0
    Jeoffrey Reyes ·
    Hi Joseph,

    Better check if the default is fine with you.
    Cheers,
  24. 0
    Ariel Malibiran ·

    p6 cannot read the backup

    p6 cannot read the backup file .prx of p3. you will be needing to restore it first to p3 files before you can import it to p6.

  25. 0
    Zoltan Palffy ·

    if you are not running a 64

    if you are not running a 64 bit operating system you can change the file extension from .prx to .exe and the selfextractor shoudl come up. If you are running a 64 bit operating system the only way to get it to self extract is ot install a virtual windows 

     

    here is the link

    http://windows.microsoft.com/en-us/windows7/install-and-use-windows-xp-mode-in-windows-7

    once you install that then you can extract the prx files to regualr p3 files then copy the files to your regular windows operating system and import the p3 project into p6

  26. 0
    Devkant Prabhakar ·

    Hello Friends, Hope you are

    Hello Friends, 

    Hope you are doing well.

    Recently I have got few PRX files to convert into P6. I can convert P3  to P6 by using old version of my Primavera Software but I am unable to see correct end date. is it due to calendar? I am not sure whether I am importing it correctly or not. I am following below steps- 

    Step01: Conversion of .PRX to EXE and extract all P3 files.

    Step02: Import files using old primavera.

    After Import we can note change in project finish date. Can Anyone plz help me. I will be very thankful for this.

    Regards, 

    DK

     

     

  27. 0
    Zoltan Palffy ·

    Make sure that when importing

    Make sure that when importing that in the import update project options that you select modify and under Data Type: Project under calendars that you select INSERT NEW my guess is that it is using the default calendar instead of the one assoicated with the project.

  28. 0
    Jonathan Goldsmith ·

    Are you referring to the

    Are you referring to the Project Must Finish By date? You may have to have the project opened to change it.

    Have you tried exporting the project form P6 as an XER and then re-importing it as an XER might fix this as well.

  29. 0
    Zoltan Palffy ·

    you do have to have the

    you do have to have the project open to change it 