P6 S Curves
In the Open Standard
Sam IsherwoodMember for 19 years 2 months
- Created
- 7
- 2
0
I'm struggling to maintain a progress S-Curve in P6.
I can set up the initial S Curve actual vs budgeted. However the next month after adding progress, I find that the original budgeted figure has changed (increased) without me changing any durations in the original planned programme.
Anyone got any sugestions to what I doing wrong?
thanks
Sam