In the Open Standard
Hossam Al-WazzanMember for 17 years 11 months
- Created
- 2
- 2
0
Greetings,
I have developed a project schedule using P6 v7, with a total float -15 days, when I do 2 weeks lookahead filter, I can see that some activities have positive float and some activities have negative float, the problem is that the total Float for all the project is showing the positive float only! it is neglecting the nagtive float! Why????
Kindly advise.