Crashing the project Schedule
- Created
- 3
- 2
Hi
I have a schedule which is resourced and I wish to do the following:
I want to crash a section of the works, so I want to indicate an increase in resources and inherently the reduction in duration. I am using Primavera P6.
To give you a background of my schedule and my intention, my schedule had programmed two similar sections of pipeline which were scheduled to be executed simultaineously for x period of time and complete at just about the same time. What happened is that the contractor was delayed because of access issues such that he could only start to work on the second section at the time the first section got completed. So now, in justifying an extension of time, the access date for the second section is revised and the sections are programmed successively instead of concurrently. Now I want to prove that if the resources that were employed for the 2nd section were allocated to the 1st section and both teams worked first on the 1st section, they would complete the 1st section earlier than it should have been and both move onto the second section.
Please advice on this matter.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?