Custom fields exporting(urgent)

Anson LoboMember for 13 years 7 months
Created
1
2
0

Can custom fields be exported ? almost 80% of my current project has been made with custom fields and global changes attached to it. if i want to use this project elsewhere i need to export the file but i need a way to export custom fields with it to. is it possible ? if not is there ANY other solution???

1 reply

Oldest first
  1. 0
    Abilash Palakkadan Mathew ·

    Yes you can export coustom

    Yes you can export coustom data with activities, you have just the fields which you want export while exporting to excel