Skip to content

S curve using duration

Peter MayMember for 14 years 8 months
Created
3
2
0

Respected planners I hail all

I am currently working on some projects which is non resource loaded and cost loaded. In my monthly reporting I am expected to report S curve of actual progress against planned. Having gone through this forumn I noticed a suggestion was made regarding using a dummy resource of 1d/d to create artificial budgeted labour units, this I have tried but realised the curve I created monthly does not tally with real situation of the projects ( there's always a wide margin difference between the budgeted units and actual units thus showing actual curve as way down the budgeted curve i.e delay  however the real situation of the project is such that the project is progressing faster than expected)

Does anyone has an idea any other metrics to draw a proper progress S curve in the absence of cost and manhours 

I am open to suggestions and welcome all ideas please 

3 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Peter,   Other than cost,

    Peter,

     

    Other than cost, resources or duration, the only measure I can think of which could be used to plot an S-curve would be activity count.

     

    Far from ideal for obvious reasons, but probably the best you can do under the circumstances.

     

    Cheers,

     

    G

  2. 0
    Peter May ·

    @ Gary,thank you for your

    @ Gary,thank you for your advice Please how does this activity count work with P6? Many thanks
  3. 0
    Gary Whitehead ·

    Peter,   Very simplistically

    Peter,

     

    Very simplistically -just give each activity a dummy resource of £1

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?