Primavera P6 - Activities In-Progress and Activities going to start

Pradyumna YarramsettiMember for 13 years 6 months
Created
1
2
0

Hi,

How do I get the activities in-progress and activities which are going to start in next 2 weeks using Primavera? Thanks for your help.

Thanks,

Pradyumna

1 reply

Oldest first
  1. 0
    Arun Kumar ·

    Hi,Right Click on Window.

    Hi,

    Right Click on Window. Click on Filters - Click on New. 

    Enter Fliter name as 2 Weeks Look ahead

    After that enter the parameters shown below

     

    where  -  start  -                is within range of           - DD                     - DD+2W

    Or       -  Activity status      - equals                        - In progress

    Mark Click on 2 weeks look head.

    Then you will get activity in progress for next 2 weeks.

    Hope you will get the solution. 

     

    Arun Kumar