Cost scale on the Y axis.

Nick JacksonMember for 19 years 3 months
Created
2
2
0

Here's something that's always irritated; is there a solution?!

When making a S curve or histogram on costs, the Y axis is always graduated at an illogical scale, i.e. if you have £1,301,123  as the max value, it graduates into say a 20% division of the budgeted total rather than rounding up on the scale to say, the nearest £100K. This gives the Y axis a strange look when presented to the team.

Is there a workaround?

2 replies

Oldest first
  1. 0
    Daniel Limson ·

    Hi Nick,If you want a combine

    Hi Nick,

    If you want a combine Line and Bar Chart, you should have a time/ Increment data and a Time/Cumulative Data

    The bar chart or histogram chart using your incremental data should be based on the Primary Axis and the cumulative chart based on a line curve should be based on the secondary axis. You can switch or define the axis by clicking on the bar or line and then format data series.

    Cheers,

    Daniel

  2. 0
    Nick Jackson ·

    Thanks Daniel

    Thanks Daniel