Mass Haul and Mirrored Activities
- Created
- 0
- 2
Hi All,
I am currently working on a mass haul programme and was wondering if there was another way to mirror an activity as a level of effort. Currently I have my cut activity linking into a cut completion milestone. And the subsequent fill activity ss à cut activity à ff with Cut completed Milestone. I want to reduce the time spent creating milestones to link the fill LOE to. Essentially I want an activity to mirror another activity in a different WBS with minimal, if any maintenance. To give you an example I have Cut from Area 1A going to Fill in Area 2B and I want to see a task dependant Cut activity in Area 1A and a corresponding LOE activity in 2B. Any help would be much appreciated.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?