Budgeted cost goes to zero on scheduling in P6 v8.2
In the Open Standard
Asish JayakumarMember for 13 years 5 months
- Created
- 1
- 2
0
Dear All,
I am faced with a problem.
I have created a programs and have given the cost for each activity as a Resource "Cost". The cost values was given in "Budget cost" column. It was all fine when I did the programs and the "Budgeted Total Cost" was also showing.
The problem was when scheduling. While scheduling all values to cost goes to zero. Why is this happening?
Pls help..
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?