Zero 'Total Float' on an activity that has no critical sucessors

Abbie PrestletonMember for 13 years 5 months
Created
3
3
0

Hi,

I have an activity that is showing as critical with zero float (total float and free float) that shouldn't be .... all of it's sucessors have at least 1 day float on them, it has no constraints, the planned start and finish, remaining early start and finish and remaining late start and finish all match the 'main' start and finish.

I've checked what is defined as being critical is anything with less than '0h' float - I don't think this should make a difference to this problem anyway as it's the number of days float on the activity that i believe to be wrong ... Any ideas as to why it would be showing zero float rather than one day?

 

Many Thanks,

Abbie

3 replies

Oldest first
  1. 0
    Warren Sika ·

    I think you better post the

    I think you better post the xer file so everybody can see what's going on inside your program. Just saying. It might help better understand your problem. I never meet such problem before. But let's wait these P6 masters arround will suggest.

  2. 0
    Vladimir Liberzon ·

    Abble,It may happen if

    Abble,

    It may happen if succeding activities have different calendar (like 6 days work week instead of five).

  3. 0
    Abbie Prestleton ·

    You're right with the

    You're right with the calendars, sub contract activities are a 5 day week and all of our succeeding activities were on 6 days ... thanks very much for your help!