Actual costs after activity has finished (lumped on Data Date)

Neil HendryMember for 14 years 5 months
Created
0
3
0

Hi

I would appreciate some help from any of you guys regarding a issue I am having with spreading actual costs (version 6.2.1)

 

I have spread a resource (material @ £1/ea) on a WBS Summary Bar that encompasses the activity bars in question however when I look at the actual cost distribution in resource assignment view some of the actual cost has been lumped on the data date (which is roughly a year after the activities had finished)

There are £0 remaining costs (as the scheme has finished)  - I have made sure that planned finish = actual finish and have checked that I haven't stored period actuals in the future by mistake.

How can I get rid of this "future actual" and ensure the entire actual sum is spread over the Actual dates?

I am unable to edit the spread manually as the values are greyed out.

Any help or pointing in the right direction would be much appreciated.

Thanks

Neil 

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?