What do i do with critical path activities in a schedule

1 reply

Oldest first
  1. 0
    Ashley Czirok ·

    The critical path is an

    The critical path is an important part of your programme, as it tells you which path is driving your end date. If any of these tasks are late, it will affect your completion date. However, I have had clients who simply don't want to see it. All they want is green! If you want to hide the critical path, press F9 to bring up the Schedule prompt. Go to options and under 'Define critical elements as', select 'Total Float less than or equal to'. In the field type -0.1h exit options and Click 'Schedule'.