Actual Labour Units
- Created
- 0
- 1
Hi,
The actual units of few activities found changing to(equal to the duration %) for the activity’s percentage complete type was Physical percentage complete.
Problem was fixed by removing the option recalculate actual units and costs when duration % complete changes, anyway root cause couldn’t find.
The discripancy observed was the activites are not responding in same manner; like if this option was the root cause the all the activities of the project should have been changed its actual units equal to duration % complete; but this wasn’t the case, this was happening only to few activities.
Please advise if you know the possible root cause.
Regards,
Abilash
Replies
Oldest firstNo replies yet. Be the first to answer.