Skip to content

Links Between Projects

Hugh McLeayMember for 14 years 7 months
Created
0
3
0

Hello,

My programme has some activities that are linked to activities in the Client's programme (local copy on my dbase). i.e. Completion of certain activities in my Client's programme defines an 'access' milestone in my programme.

What does P6 do with these links if I export my project only, and send it to someone?

If someone else imports my XER file, will all my 'access' milestones revert to the data date? or will they be constrained in time?

If the person I'm sending the XER file to also has a copy of my Client's programme, will P6 re-establish the links to their version of the Client's programme?

Thanks,

Hugh.

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?