Filtering out the spotlighted activities

Thomas NicholsonMember for 20 years
Created
1
2
0

Hi there,

Can anyone tell me how when using the spotlight to highlight a period of time I can show on the task list only those highlighted and nothing else?

I've tried a filter but can't seem to find anything that will select a range of dates rather than a start or end date. For example I want to show anything from 2 weeks ago to 2 weeks in the future whether it's started, ended or currently in progress with a start or end date before or after my range of dates.

any assistance greatly appreciated.

Cheers

Thom

1 reply

Oldest first
  1. 0
    Håkon Haukebøe ·

    Edit: I dont know why the

    Edit: I dont know why the image disapeared. Here is the filter you should try:

    Any of the following:

    Where start is within range of CD-2W CD+2W

    Or Finish is within range of CD-2W CD+2W

    Or Activity status equals In Progress.

    Please tell me if this helps. Can email you the screenshot of the filter if you want.

     

    H

     

    try this:

    Create a new filter:

    This should give you any activity started or ended within CD (current date) +/- 2 weeks, and any activity in progress.

     

    Cheers

     

    Haakon