as late as possible

Raed HusseinMember for 19 years 4 months
Created
5
2
0

i use this type of constraint to link engineering activities with construction activities is it right ? if not pls advise me

5 replies

Oldest first
  1. 0
    Feng Benjamin ·

    Dear RaedThis logic only

    Dear Raed

    This logic only works if you have ensured there are no "open" activities. Having a missing link would result in these activities being measured from the end of the entire project.

    Warmest Regards,
    Benjamin

  2. 0
    Gary Whitehead ·

    I would advise against.If the

    I would advise against.

    If the engineering task is just 1 day late, it will delay construction. And since engineering activities are notoriously difficult to predict and control, this is quite a risky approach.

     

  3. 0
    Mike Testro ·

    Hi GaryI disagree.Having

    Hi Gary

    I disagree.

    Having engineering tasks linked to construction by ALAP gives the correct delivery date for the design.

    If the construction slips then the designers have more time.

    If the design slips then the construction is delayed.

    I would usually put a 5 day buffer on the link and have the "Traffic Lights" set to 5 days.

    Best regards

    Mike Testro

  4. 0
    Gary Whitehead ·

    Hi Mike, I would say using

    Hi Mike,

     

    I would say using ALAP gives the latest delivery date for the design deliverable, not the correct one.

    I prefer to plan engineering tasks to happen as early as possible (allowing for limited engineering resources, and prioritised on free float). They often slip, but this way you have the max amount of buffer before slippage becomes an issue.

     

    Another point to note is that if you are using ALAP, be sure you have allowed enough time for any procurement required before construction can commence.

     

    Cheers,

     

    G

  5. 0
    Raymund de Laza ·

    Hi,I use ALAP for engineering

    Hi,

    I use ALAP for engineering and may input 1 month buffer just to establish the possible start. After establishing the start of engineering, either use a lag from the Engineering Start or Start Constraint then remove ALAP.

    This will give Tech Dept time to prepare and a buffer before construction.

Log in or join to reply