difrence between orignal duration & at completion duration

Rizwan KhanMember for 14 years 1 month
Created
2
3
0

Dear all

 I had problem with the duration which i was working , there is 

 

 

 

what is diffrence between orignal and at copletion duration , how we can use it  in primevera 

thanks you all

2 replies

Oldest first
  1. 0
    Rajesh Kumar ·

    hiOrginal Duration -planned

    hi

    Orginal Duration -planned duration 

    at cmpt duration nothing but  actua work performed during project

  2. 0
    Arnold Puy ·

    Hi Rizwan,The Original

    Hi Rizwan,

    The Original duration is the number of working days required to complete each activity based on the current schedule. However, At completion duration is the sum of the actual duration and the remaining duration.

    Cheers,

    Arnold