Planners,
I work in the overhead line transmission industry, this mainly depends on client outages in order for us to carry out work.
So basically as soon as an outage begins we can start work on the refurbishment of conductors etc, we have a set time to which the outage will run so all work to do with the outage has to be completed by outage finish.
In my programme I show all pre outage works, ie steelwork replacement as well. The last activity in the pre outage works may have some float before the outage starts. Then the outage works begins.
When the outage finishes there will be other work to do like reinstatement of sites etc.
My question is, how do we show that outage? I did have the outage represented by a start and finish milestone, the problem was that the critical path only ran from my outage finish mielstone to the project end. I need to show the critical path through out the project ie design>procurement>construction
What would the best way to maintain having a critical path and showing the outage?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?