how to convert duration to weight in primavera ?
In the Open Standard
Irfan KhanMember for 17 years 3 months
- Created
- 5
- 2
0
hi to all experts,
here i am searching a way in primavera which is that how to convert my Original Duration to weight ?
Some details are here :
My manager asked me to load overall project cost only to Construction Phase. But for Engineering & Procurement phases
you have to measure based on duration.
He wants to map the of % of completion for all 3 phases i.e. (Engineer, Procurement & Construction) separately.
Plz if anyone knows the way, kindly share with me. I will be highly obliged.
thanks in advance…..
5 replies