Problem - Resources being phased after activity completion

Stephen HobbsMember for 20 years 1 month
Created
3
3
0

Hi

This relates to P6 release 6.0

We are noticing a problem where the resource histogram profiles are running well past the activity completion dates.

Does anyone have some idea as to why this is happening?

We think it may be a software error where a previous resource phasing distribution has not been removed/replaced.

3 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Stephen,I suggest to

    Stephen,

    I suggest to investigate the Calendar assigned with the Resources. View the Start and Finish date of the Primary Resource.

     

    Hope this will help.

  2. 0
    Khaja Sharief ·

    One more reason could be

    One more reason could be that, there are activities with negative float which is because of unsatifactory constraints attached to activities in the network. Remove the constraints to the activities connected with the activity's network path.

  3. 0
    Andrew Podolny ·

    Please also ensure that the

    Please also ensure that the drive activity dates is checked on and the lags are 0 for your resource assignment:

Log in or join to reply