want to extract Activity Usage Spreadsheet on desired WBS

Irfan KhanMember for 17 years 3 months
Created
1
1
0

hi to all,

i am searching a way to extract Activity Usage Spreadsheet from P6 to Excel for desired WBS.

i have loaded cost on Engineering, Procurement & Construction Phases & my Performance Percentage Complete is 12.72%.
here i want to see Planned & Actual Cost only for my Construction phase in Activity Usage Spreadsheet. I tired by using filter as well but it didn’t work.

Would anyone please tell me how to solve this issue.

thanks….

1 reply

Oldest first
  1. 0
    Arnold Puy ·

    Hi Irfan,In order to perform

    Hi Irfan,

    In order to perform this please follow the following steps as shown below:

    1. Go to --> Edit --> Select All, when done, again Edit --> Copy

    2. Open an Excel sheet and select Paste

     

    You can also go to View --> Group & Sort 

    Hope this helps.

    Cheers,

    Arnold