P6.1 Reporting - Budgeted Monthly Cost
In the Open Standard
Adelfa SapinosoMember for 19 years 3 months
- Created
- 1
- 15
0
Dear Planet,
How to produce a report where the total budgeted cost is distributed monthly in P6.1? I am only able to produce a report where the activity budgeted cost shows on the first month and not distributed for the whole period :(
e.g. jan2013 feb2013 mar2013
activity101 $1,000 $1,000 $1,000
my report shows:
jan2013 feb2013 mar2013
activity101 $3,000
Thank you ahead!