Filter activities that has changed compared to assigned basline

Håkon HaukebøeMember for 14 years 1 month
Created
5
2
0

Hi all. Does anyone know how to create a filter wich only shows the activities that has changed (start or finish) in current plan compared to assigned baseline?

 

cheers

 

Haakon

5 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Filter on: Where Variance

    Filter on:

     

    Where Variance - BL Project Finish date is not equal to 0

    Or Variance - BL Project Start date is not equal to 0 

     

     

    Cheers,


    G

  2. 0
    Muhammad Anwar ·

    Haakon   Filter on Baseline

    Haakon

     

    Filter on Baseline Start or Finish Variance

     

    Regards

  3. 0
    Håkon Haukebøe ·

    Thanx, that works. Only thing

    Thanx, that works. Only thing i miss is that new activities (activities not in baseline, but in current project) seem to fall out. How can I include them?

  4. 0
    Håkon Haukebøe ·

    thanx alot. Haakon

    thanx alot.

     

    Haakon

  5. 0
    Arnold Puy ·

    Hi Hakon,Check this out

    Hi Hakon,

    Check this out

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

    Cheers,

    Arnold