How to display resource usage profile for filtered activities only

Asish JayakumarMember for 13 years 5 months
Created
2
6
0

Hi all,

I am facing a problem.

I have created a programme and filtered some activities using Activity codes.

I want the resource usage profile for the filtered activities alone.

How can this be done?

-AJ

2 replies

Oldest first
  1. 0
    Asish Jayakumar ·

    I am using Primavera P6

    I am using Primavera P6 R8.2.

    -AJ

  2. 0
    Arnold Puy ·

    Hi Asish,You can filter the

    Hi Asish,

    You can filter the group of activities using activity codes; however it is not possible to show or filter only the lists of the Resources assigned to those activities displayed while currently showing the “Resource Usage Profile” bottom layout.

    I suggest you may use the functionality of “Tracking” which show only those resources assigned to each WBS level.

    I hope the above assists you.

    Cheers,

    Arnold