Baseline is not correct
In the Open Standard
Jeff HogervorstMember for 13 years 1 month
- Created
- 6
- 8
0
I am new to P6 and I'm new to Planning Planet.
So far I have;
- I am trying to compare 2 schedules; 'Pre-Impact' and 'Post-Impact'. I have progressed the two schedules to different dates (including actual dates and any re-sequencing).
- Both of the above schedules were created by copying an earlier schedule.
- I've assigned the 'Pre-Impact' schedule as the Baseline (Project Baseline AND Primay Baseline) in the 'Post-Impact' Schedule.
Issue: The Baseline schedule in 'Post-Impact' does not match the dates in the 'Pre-Impact' schedule.
I've tried;
- Removing the 'Pre-Impact' as the Baseline then re-assigning it.
- Closing Primavera and restarting
- Refreshing the page
- Double checking the dates in 'Pre-Impact'
Question: Does anyone have any suggestions as to how to get my Baseline to reflect the 'Pre-Impact' schedule?
Thanks in advance,
- Jeff
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?