Primavera v 6.2 to 8.2 - WBS Summary Duration using Global Calender
In the Open Standard
Melvin PerezMember for 18 years
- Created
- 1
- 3
0
Hi to all experts,
After migrated form Primavera v 6.2 to 8.2 i have problem wbs summary duration. I import file to latest version but when I choose global calendar default (ex 7 days or 6 days/week calander) wbs summary duration not changing in R8.2 but in V6.2 it works.
Kindly provide me asisstance to anyone know solution of this problem?
Thanks in advance.......
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?