updating of tasks

Steve CraineMember for 24 years
Created
2
1
0

Hi people

 

Hope you can help, something that has just started happening in my version of P6 ver 7

I create a schedule, with logic links in etc when I hit F9 to schedlue all the tasks come back

to start on the data date therefore destroying the schedule any ideas????

Thanks

Steve

2 replies

Oldest first
  1. 0
    Kaif Mohsin ·

    Dear Steve,If the tasks are

    Dear Steve,

    If the tasks are already having the actual dates & percentages, then check for the 'Retained Logic' instead of 'Progress Override' options under the 'Options' button in the 'Schedule' tab.

    Best Regards,

    Kaif Mohsin 

  2. 0
    Steve Craine ·

    Thanks Kaif sorted the

    Thanks Kaif sorted the problem