commas in cost accounts
- Created
- 2
- 1
Hi
I've allocated cost accounts to the resource allocation on an activity but, when organising in the activity layout to report on EV per cost account, it groups by 'mech labour' and mech labour,' with a comma.
It does this for some of the costs accounts but not all. when I check the cost accounts on the activities, they are the same cost account. If I group by cost account in the resource assignment tab, it groups them under one i.e. 'mech labour'. But I can't report on EV in this layout.
is there any reason why a comma separates activities which have the same cost account allocated?
Thanks
2 replies
Oldest firstLog in or join to reply