Skip to content

Drive Activity Dates

mani M.RMember for 17 years 2 months
Created
0
2
0
Hai

Some of the activity Resource Original Duration is not Equal Activity original duration .
 
This issue occur where single activity have Multiple resource . 
 
Activity Type is task Dependent , Duration type is Fixed Duration & Units /Time, Percentage Complete is duration
 
Whether Default Drive Activity Dates option is to be Clhecked even the Activity Type is task dependent (Drive Activity Date option will be checked where Activity Type is Resource Dependent)
 
 
Regards
Mani
 
 
 
 

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?