Can assign same resource to different activities/projects at same time in p6 v8.2 ???

G AbbasiMember for 13 years
Created
2
3
0

Hello Every One,

Can we assign same resource (e.g  electircal technician) to differenct projects or withins same project at same time in primavera p6 r8.2.

I am trying to manage my department resources on multiple projects, one resource not to assign multiple acitivities at same time acitivities.

Please help

Thanks 

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello,Select all the

    Hello,

    Select all the activities you want to assign a specific resource to, then select the resource and click the assign button

    Then select on activity at a time to see the assignment in the Activity Details Pane

    Alexandre

  2. 0
    G Abbasi ·

    Thanks for your

    Thanks for your response,

    Exactly i wanted to know that how to prevent to reduce the over-located the resource in multiple activities. 

    In MS Project it, if any resource assign to two different activities in between the duration of time, it indicates resource over-located mentioned in figure. But in P6 i didn't found like this.

    Can any one know about this to how to do this in P6.

     

Log in or join to reply