Duration error - I entered days & it took it as hours.

Shishir DhatwaliaMember for 13 years 1 month
Created
2
1
0

I am new to P6 using P6v7.

I entered activities & their durations the normal way & added resources to the activities. It is showing like this: -

Original Duration Column as 20d [ fine as I entered 20 ]

Budgeted Units as 20h in Bottom Layout - Resources TAB. [ when i entered 20 as days, it took as hours]

This affected my Budgeted Total Cost Column, as my cost is taking the durations from the resources (in hrs.)

 

can anybody help, i guess some adjustment required in Preferences but i don t know where.

 

 

2 replies

Oldest first
  1. 0
    Håkon Haukebøe ·

    Try:Edit - > user preferences

    Try:

    Edit - > user preferences - > Time units. There you can choose Units and Durations to Day.

     

    Haakon

  2. 0
    Shishir Dhatwalia ·

    it worked thanks

    it worked 

    thanks