Skip to content

Default Units/Time for Resource not working

Adam GarnhamMember for 15 years
Created
0
4
0

Hi guys,

 

So I have a new resource with Default Units/Time of 5h/d and Max Units/Time of 5h/d. This resource is assigned to an activity which is Resource Dependant. When I view the resource allocation spreadsheet is has phased remaining units as 3h/d?

The Resource calendar hours are less than the activity calendar so there is room there to do 5 h/d but for some reason it isnt? Any ideas?

Duration type for the activity is fixed units/time.

 

Cheers

Adam

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?