Default Units/Time for Resource not working
In the Open Standard
Adam GarnhamMember for 15 years
- Created
- 0
- 4
0
Hi guys,
So I have a new resource with Default Units/Time of 5h/d and Max Units/Time of 5h/d. This resource is assigned to an activity which is Resource Dependant. When I view the resource allocation spreadsheet is has phased remaining units as 3h/d?
The Resource calendar hours are less than the activity calendar so there is room there to do 5 h/d but for some reason it isnt? Any ideas?
Duration type for the activity is fixed units/time.
Cheers
Adam
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply