Incorrect progress line

Richu RoseMember for 19 years 8 months
Created
1
2
0

 don't know if any one of you have encountered but I am getting incorrect progress line, if planned & actual progress is 0% progress line shows to the left side of data line and sometimes if actual progress is more then planned still the progress line will be to the lft side of data line.

I am using P6V7

Regards,

Richu

1 reply

Oldest first
  1. 0
    Johannes Vandenberg ·

    Hi RichuNote that the

    Hi Richu

    Note that the progress line is drawn on the basis of the assigned baseline. So, if the progress of an activity is less than the planned progress of the baseline schedule, the progress line shall be to the left side of the Data Date. Spot on the Data Date if the progress equal to the baseline date schedule. The same applies for activities ahead of schedule, the progress line shall be to the right.

    Please also note that by reporting physical % completion type that not only the % needs to be entered but also the remaining duration.

    Regards Johannes