Hi All

 

I’m working on a power station project, and have to input the disruption dates of the “strike action” into my program.

 

Could someone advise me on how I can show these disruption dates through the entire schedule. I have 4 sets of dates to input into my schedule.

 

Kind regards

 

Robert

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi RobinPut them on the

    Hi Robin

    Put them on the calendar as non working days

    If part working then set up new work patterns to suit.

    Best regards

    Mike Testro

  2. 0
    Gary Whitehead ·

    Robert, What is the nature of

    Robert,

     

    What is the nature of the disuption? -Will it be a case of no work occuring during the strike action, or will the work continue, albeit at reduced productivty?