Bringing activity details to project level
In the Open Standard
Mark HeardMember for 22 years 7 months
- Created
- 2
- 2
0
Hello,
I am trying to create the foundation for a report resembling the table below, where the milestone is extracted from each project. I have looked into activity codes, but can't work out how to bring that information up to a project level.
Table:
| ProjID | ProjName | Start | Finish | Milestone |
| 001 | Proj-001 | 01/01/2013 | 01/06/2013 | 01/03/2013 |
| 002 | Proj-002 | 02/02/2013 | 01/07/2013 | 01/04/2013 |
| 003 | Proj-003 | 03/03/2013 | 01/08/2013 | 01/05/2013 |
| 004 | Proj-004 | 04/04/2013 | 01/09/2013 |
01/06/2013 |
Any guidance would be appreciated.
Using P6 R8.3 Professional and Enterprise
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?