Reducing budgeted labor units by 10% for a large number of tasks

Jean DesjardinsMember for 14 years 11 months
Created
2
2
0

Hi everyone,

Does anybody know how to reduce the budgeted labor units by 10% for a large number of tasks in P6 ?

I tried using global change but did not find budgeted labor units in the drop menu.

Thanks

2 replies

Oldest first
  1. 0
    Raymund de Laza ·

    On the Global Change.. in

    On the Global Change.. in Subject Area select Activity Resource Assigngment...

  2. 0
    Jean Desjardins ·

    Thank you Raymund

    Thank you Raymund