Display total float on Project level
In the Open Standard
Ahmed KHRMember for 15 years 11 months
- Created
- 1
- 2
0
Dear Primavera Experts,
My question is, How can I display the total float on the Project summary level?
The project completion milestone delayed 68 days (TF=-68), But on the project level it shown (TF=0), how can I display on this level the same TF whatever it's negative?
Please view the picture below.
NB.I use P6 R8.3
Thank you for your help in advance.