Skip to content

Display total float on Project level

Ahmed KHRMember for 15 years 11 months
Created
1
2
0

Dear Primavera Experts,

 My question is, How can I display the total float on the Project summary level?

The project completion milestone delayed 68 days (TF=-68), But on the project level it shown (TF=0), how can I display on this level the same TF whatever it's negative?

Please view the picture below.

NB.I use P6 R8.3

Thank you for your help in advance.

 

1 reply

Oldest first
  1. 0
    Ahmed KHR ·

    I get it, I must add Must

    I get it, I must add Must finish date to project to get this TF.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?