How to filter activities progressing between two dates?

Pranab Kumar DebMember for 19 years 9 months
Created
2
23
0

Hi All,

I want to filter activities between two dates in future, lets say 1June2014 and 30June2014. I am on P6.1, I would want to filter all activities including the ones having early dates inbetween and the ones progressing, i.e. started in April or May and progressing in June of 2014.

Thanks,

Pranab

  

2 replies

Oldest first
  1. 0
    Jean Desjardins ·

    Create a filter "All of the

    Create a filter "All of the following" with early start less than or equals June 30 2014 and late finish greater than or equals June 1st 2014

  2. 0
    Pranab Kumar Deb ·

    Hi Jean, Thank you for your

    Hi Jean,

    Thank you for your reply!

    It has to be

     

    Early Start < 30June2014

    Early Finish > 1Jun2014

     

     

    Thanks a lot!

     

    Pranab

Log in or join to reply