activity usage profile - Need to Show Values

Premod JacobMember for 12 years 11 months
Created
3
3
0

Hi,

Good Day !!

 

Is sit possible to show the unit values at the top of each bars in Activity Usage Profile Histogram in P6..?

3 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Jacob,Use the Bar Labels.

    Jacob,

    Use the Bar Labels.

  2. 0
    Premod Jacob ·

    Hi De Laza,I want that labels

    Hi De Laza,

    I want that labels / values in the Acivity Usage Profile Histogram, not in Ghant Chart.

    Is there any option to give a label / unit in that Histogram printout ?

  3. 0
    Raymund de Laza ·

    That's not possible. Suggest

    That's not possible. Suggest to Transfer the Data to Excel.