Skip to content

P6 Rel 6.2.1 Resource Assignments

George LeatherMember for 22 years 3 months
Created
1
1
0

I am assigning several resources to the same activity with budgeted quantities, progress % and remaining hours to complete.

I then need to view each of these resource assignments using the "resource usage profile" view so I can see the bars showing the work to complete.

The problem I have is that I cannot summarise the resources by activity, the activity will be visible but with all the resources listed as the header.

I know this can be done using "assignments" but this doesn't display the bars, only hours in a spreadsheet.

I have tried to filter out the individual resources by activity but so far unsuccessful.

1 reply

Oldest first
  1. 0
    Raymund de Laza ·

    You may create Activity Codes

    You may create Activity Codes = Activity Name, Assign the Activity Codes to corresponding Activity then Use the Group and Sort to Organized by Activity Code.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?