Primavera setting to keep deleted Activity IDs from being automatically generated
In the Open Standard
Chris FeaganMember for 12 years 11 months
- Created
- 1
- 2
0
Is there a Primavera setting that will keep deleted Activity IDs from being automatically generated in Primavera 6 Rev 8.2?
We normally utilize the "auto-numbering" capabilities within Primavera, but have noticed that deleted Activity IDs are being re-created, thus causing some confusion in our network. Because there are numerous personnel that report on our data, the fact that Activity IDs are regenerated after a task in deleted causes the major confusion.