can i change 1 word within multiple activity names?
In the Open Standard
Ashley ReevesMember for 13 years
- Created
- 2
- 2
0
hi all
i have been given a plan to run that i didnt build myself and the plan has a few errors, there is around 200 tasks that are identifying the wrong peice of equipment were working on so rather than change each 1 individually i was wondering if it is possible to use global change and somehow find the word im looking for within all tasks and replace with another??
any help would be greatly appreciated
thanks
once i have a few years experience with the software i shall make a point of helping out others like i have been helped out on here
2 replies
Oldest firstLog in or join to reply